16 May May we show you what’s Under-Construction: Sea Level gets a Face Lift!
Continuing through May, here is a status update on our Sea Level Project in Malibu. We have FINALLY started construction on the Phase 2 remodel which will completely change the front Facade of this 80’s architectural Beauty!
Concept sketch showing the revised Front Facade to capture the view of the Pacific! Sketch by MAST
Look at that View!
Now its time to show how the transformation is progressing…
What it looked like before…
What it looks like now… a little like swiss cheese… Or like zombies got to it…
Master Bedroom Rotunda View. Its nice to see the drawings on site!
Let’s start framing the new Master Bath!
Watch your Step! Future Master Bedroom Balcony.
Thats a lot of temporary framing… but look at that peek-a-boo view through the studs! Main Level Entry.
What’s next? New concrete Pile foundations and Steel framework to support that expansive sliding door. Stay Tuned!
See our other posts on this project:
Project Spotlight: Sea Level Dr.. but in 3D!
Project Spotlight: Sea Level Dr